Blog > Taking Possession of a New Build in Ottawa This Winter: The PDI, Your 30-Day Form and What Can Wait Until Spring

Taking Possession of a New Build in Ottawa This Winter: The PDI, Your 30-Day Form and What Can Wait Until Spring

by Dan Jutai

Twitter Facebook Linkedin

New homeowner crouched on a gravel driveway in light snow, photographing the bare, ungraded front yard of a new townhouse

If you take possession of a new home in Ottawa this winter, you will do a pre-delivery inspection (PDI) with the builder first, then you have the first 30 days after possession to send Tarion your 30-Day Form listing anything still wrong or unfinished. The PDI form on its own is not a warranty request.

Some outside work is allowed to wait for warmer weather. Exterior painting, concrete, mortar, stucco and caulking generally get finished between May 1 and September 1. Final grading, sod, driveways and walkways run on a longer clock that only counts days between May 1 and November 15, so after a winter closing they can stretch into your second summer.

What happens at the PDI?

The PDI is a walk-through of the home that the builder leads before you move in. According to Tarion's PDI page, its purpose is to record anything that is incomplete, damaged, missing, inaccessible or not working properly. Those items go on the builder's PDI Form, which becomes the official record of the home's condition before you move in.

A few things are worth knowing before you go:

  • You, or someone you name as your designate, has to be there. If you send a designate and want them to sign, the builder needs your written authority on Tarion's Appointment of Designate form.
  • You sign the PDI Form to confirm the list is complete and accurate. You also sign a Certificate of Completion and Possession, which records your possession date. That date is the day your warranty starts.
  • You can take photos of anything damaged or unfinished. They are useful later if an item is disputed.
  • Ask for copies of the completed PDI Form and the certificate before you leave.

If you want a professional with you, sort that out with the builder ahead of time. Our guide to what home inspections in Eastern Ontario cover and miss is a good read on what a second set of eyes can and cannot tell you.

Why does a winter PDI need extra care in Ottawa?

In an Ottawa winter, snow and frozen ground hide a lot of the outside of a new home. Grading, the driveway base, walkways, the bottom of the siding and any exterior concrete may be partly or completely covered when you do the walk-through.

Tarion says items you cannot inspect because of weather, or because they are covered or not accessible, should be noted on the PDI Form. Write down what you could not see, not just what looked wrong. It costs nothing and gives you a clear record of what still needs a look in spring.

Inside, winter also tests the heating right away. Tarion treats a complete loss of heat between September 15 and May 15 as an emergency. If the builder does not fix an emergency within 24 hours, you contact Tarion.

Which forms do you send, and when?

The PDI list is a starting point, not a claim. To get warranty service you submit a form to Tarion, and the timing matters. Tarion's page on how to make a warranty claim lays out the windows, and its preferred way to submit is MyHome, its online portal.

Form When you can send it Worth knowing
30-Day Form During the first 30 days after possession. You can send only one. Include anything from the PDI that is still not fixed, plus anything new you have found.
Year-End Form During the last 30 days of your first year. Only one is accepted. It is your last chance to report items under the one-year warranty.
Second-Year Form Any time in the second year. You can send more than one. It covers items under the two-year warranty.
Major Structural Defect Form After the second year, up to seven years from possession. You can send more than one.

Once a form is in on time, the builder gets an initial 120-day repair period. If items are still not resolved at the end of it, you have 30 days to contact Tarion and ask for a conciliation. If you do not, Tarion says the items on that form are withdrawn. Put those dates in your calendar the day you send the form.

What can wait until spring?

Tarion's page on exceptions to the regular claims process explains that some work depends on the weather, and it treats May 1 to November 15 as the period that is generally suitable for it. There are two groups, and they run on different clocks.

Seasonal exterior items

These include exterior painting, exterior concrete and parging, exterior mortar and brick, stucco, exterior caulking and in-ground supports for decks. If weather stops the builder from finishing them, the builder has to complete them as soon as suitable weather returns, and in any event between the following May 1 and September 1. If you are not satisfied, you have until October 1 to contact Tarion. After that, Tarion considers those seasonal items resolved.

Final grading, sod, driveways and walkways

These are treated separately. For items listed on your warranty form, the builder has 270 days of seasonable weather from your possession date, unless a longer period was agreed or set by a municipal agreement. Only days between May 1 and November 15 count, which is 199 days in a calendar year.

That is why a winter closing feels so slow on the outside. As a rough illustration, if you took possession in December 2026, no days would count until May 1, 2027. That season gives 199 days, leaving 71 to run from May 1, 2028, which lands around mid-July 2028. Tarion's Registrar Bulletin sets out the exact calculation, so confirm your own date with the builder or Tarion rather than relying on this example. If the work is not done by day 270, you have 30 days to contact Tarion and ask for an assessment.

The practical takeaway: a bare yard and a gravel driveway in January are normal for a new build, but they still belong on your 30-Day Form so the clock and the record are both on your side.

Your first 30 days after a winter possession

  • At the PDI, note anything you could not inspect because of snow, ice or access, not just visible defects.
  • Take dated photos of the yard, driveway, walkways and exterior finishes as they are at possession.
  • Keep copies of the PDI Form and the Certificate of Completion and Possession, and write down your possession date.
  • Set up your MyHome account with Tarion so you can submit forms online.
  • Send your 30-Day Form before day 30, including unfinished PDI items and outstanding grading, sod, driveway and walkway work.
  • Ask the builder whether any municipal agreement gives a longer period for grading or paving on your lot.
  • Put the 120-day repair period and the 30-day conciliation window in your calendar.
  • If the heat goes out completely, call the builder right away and contact Tarion if it is not fixed within 24 hours.

Common follow-up questions

Is the PDI the same as a home inspection?

No. The PDI is the builder's walk-through to record the home's condition before you move in. It is not a warranty claim and it is not an independent inspection. If you are still deciding between a new build and a resale home, our new construction vs resale guide covers how the two paths differ before you sign.

What if I find something after I move in?

Tarion says to document it and report it to the builder right away, for example with photos and an email. Then make sure it goes on your 30-Day Form, or the next form that is open to you.

Does a missing item on the PDI Form cancel my warranty?

According to Tarion, not noting an item on the PDI Form does not necessarily affect your warranty coverage. The form is still useful evidence if there is a disagreement later, which is why a careful list helps.

Closing on a new build in Ottawa this winter?

Happy to talk through your dates and what to watch for at the walk-through. Get in touch. No pressure either way.

Sources: Tarion, The Pre-Delivery Inspection; Tarion, How to make a warranty claim and what to expect; Tarion, Exceptions to the regular claims process; Tarion, Six warranty terms you'll want to know. All were read November 21, 2026.

Warranty rules and timelines can change, and your builder agreement may add details. Confirm your own dates with Tarion and your builder, and get legal advice on your purchase agreement.